Lubricant Workshop Upgrade and Renovation Project of FUCHS Lubricants (Yingkou) Co., Ltd. Environmental Impact Assessment (First Public Notice)
Beijing Zhongzihuarui Engineering Technology Co., Ltd. was entrusted to carry out environmental impact assessment for the lubricant workshop upgrade and renovation project of FUCHS Lubricants (Yingkou) Co., Ltd. According to the relevant provisions of the "Measures on Public Participation in Environmental Impact Assessment", FUCHS Lubricants (Yingkou) Co., Ltd., the construction unit, hereby publishes the following information to the public:
1. Name and Overview of the Construction Project
Project Name: Lubricant Workshop Upgrade and Renovation Project of FUCHS Lubricants (Yingkou) Co., Ltd.
Project Overview: The project is located in the existing factory of FUCHS Lubricants (Yingkou) Co., Ltd. As three production lines with production processes that are the same as the original need to be added in the lubricant workshop to expand lubricant output, equipment such as exhaust cylinder, saponification tank, mixing tank, post-treatment equipment and other ancillary equipment shall be added in the lubricant workshop, thus increasing the annual production capacity by about 2500 tons. At the same time, a boiler room shall be built to include a new 2400 KW heat-transfer oil heating furnace. The total investment is 16 million yuan.
Nature of Construction: Reconstruction and Expansion
2. Name and Contact Information of the Construction Unit
Name of the Construction Unit: FUCHS Lubricants (Yingkou) Co., Ltd.
Contact: Li Yuanyi
Tel.: 15141732077
Mailing Address: No.10 Jiachen Avenue, Coastal Industrial Base, Yingkou City, Liaoning Province, China
3. Name and Contact Information of the Unit In Charge of Environmental Impact Assessment
Unit In Charge of Environmental Impact Assessment: Beijing Zhongzihuarui Engineering Technology Co., Ltd.
Mailing Address: Room 19-4, 19/F, Building 57, No. 2 North Jingyuan Street, Beijing Economic and Technological Development Zone, Beijing, China
Contact: Wang Gong
Tel.: 18340622456
4. Working Procedures and Main Working Contents of Environmental Impact Assessment
Working Procedures: Commissioning - Status Survey - Public Survey - Preparation of Environmental Impact Report - Report Review - Report Approval.
Main Working Contents: Evaluate the regional environmental characteristics by investigating the environmental status of the surrounding area of the construction project, conduct engineering analysis, determine the environmental impact factors, demonstrate the feasibility of pollution prevention and control measures, predict and evaluate the environmental impact during the construction period and operation period of the project, and give a clear conclusion on the feasibility of the project construction from the perspective of environmental protection.
5. Main Means for the Public to Submit Opinions
The public may submit written opinions to the construction unit in the form of letters, faxes, e-mails, etc.
6. Web Link to the Public Opinion Form
http://www.mee.gov.cn/xxgk2018/xxgk/xxgk01/201810/W020181024369122449069.docx